Completion of the modernization of the 220 kV overhead power line Kozienice – Rożki

At the end of September, #EltelNetworksTeam successfully completed the modernization of the 220 kV overhead power line Kozienice – Rożki, Poland. The subject of the task was to perform the necessary modernization works, including:

  1. Replacement of 20 existing poles along with foundations, insulation, marking, grounding and anti-corrosion protection:
    • on the double-track section: 133 and 134
    • on the single-track section / track I: 94, 95, 111, 112, 113, 114, 125, 126, 127 and 128
    • on the single-track section / track II: 99, 110, 111, 112, 113, 114, 120 and 128
  2. Raising 6 towers:
    • on the double-track section: 28, 61, 77
    • on the single-track section / track I: 106, 107 and 109
  3. Obtaining a transmission easement for 26 towers to be replaced or raised.
  4. Adjusting the sag of phase conductors in 11 sections along with anti-vibration protection.
  5. Replacement of the existing OPGW cable with a new 48J cable on track I (14 fiber optic sections with a total length of approx. 52.5 km).
  6. Replacement of the existing traditional lightning conductor with OPGW 48J on track II (14 fiber optic sections with a total length of approx. 53 km).
  7. Anti-corrosion protection of existing pole structures (157 positions).
  8. Replacement of selected insulator strings on the overhead line.
  9. Introduction of fiber optic routes to Kozienice and Rożki substations.

Our commitment, professionalism and attention to the highest quality of workmanship contribute to increasing the security of power supply and energy security of the country, this time in Masovia region.
Well done #EltelNetworks Team! Thank you all for the excellent execution of the task!