Completion of the construction of the 110 kV Klementowice - Nałęczów and 110 kV Klementowice - Puławy Rudy power lines

In December 2023, we completed the construction works and carried out technical acceptance of the 110 kV power line Klementowice - Nałęczów and the 110 kV Klementowice - Puławy Rudy power line. Currently, formal and legal works are still underway to complete the entire investment.
The scope of activities performed by #ZałogaEltelNetworks includes:

  • dismantling of phase conductor lines, insulation, poles and foundations
  • construction of new foundations
  • setting of lattice towers
  • suspension of new phase cables
  • installation of line markings (numbering, information, aviation and warning boards)
  • relocation of the existing OPGW cable to new pole structures while maintaining the continuity of OPGW cable connections

The reconstruction performed by Eltel Networks included:
110 kV Klementowice – Nałęczów power line

  • prefabricated foundations 41 sets.
  • steel structures (towers) 41 pcs.
  • total length of the line 11,17 km

110 kV Klementowice – Puławy Rudy power line

  • prefabricated foundations 29 sets.
  • steel structures (towers) 29 pcs.
  • total line length 8,038 km

Congratulations to our brigades involved in the implementation of this successful project!